FROOZAN Off-Shore Wellhead Platform F-18
Scope of service
Among several smaller items of equipment, the following main services was supplied.
Site Visit, Check Foundations, AHU & ACU Visual Check, Find Out Piping & Cabling Route.
Design Interconnection Copper Pipe Size& Route For Liquid &Suction Line
Material Take Off Configuration Including Copper Pipe , Elbow ,Connectors, Support, Insulation,…
Hanging & Installation AHU units on Base Frame With Vibration Absorbers Pad
Reassembling Ahu's Section By Stiffeners
Hanging & Installation ACU units on Base Frame With Vibration Absorbers Pad
Pipe Cutting , Fitting , Install Pipe Support ,Silver Brazing ,painting ,…. For Each Circuit .
Washing Circuits By Refrigerant R141-B
Nitrogen Pressure (Leak) Test for 24 to 48 hours According to the Site Specification And Remove Leakages
Install Insulation And Cladding.
Connect All Wires To Local & Control Panel And Instruments
Install All Instruments Such TT,HT,Pressure Transmitter ,Motorized Damper,...
Logic Test , Check Machine Inside Controllers & Switches.
Vacuuming ,Set The Core Driers , Change The Compressor Oil
Cleaning &Washing Machine Coils , All inside Equipment and Install AHU's Filters.
Charging refrigerant , Start-Up Circuits Separated And Partially.
Operation & Maintenance For 48 Hours Non Stop Working.
SAT activities
Check the acceptance criteria
Clients expert training
Performance Test