FROOZAN Off-Shore Wellhead Platform F-18


FROOZAN oil field in the persian gulf is under reconstract and development and wellhead platform F-18 was built by PFC engineering and construction co for the iranian offshore company (IOCC co) during 2015 to 2018 ,It is designed to conduct the traditional offshore tasks as well as wellhead operations . ARMANIK was responsible for the copper pipe-work , commissioning and testing of the HVAC systems' as follows :
 
LV room
MV room
Rest room
Battry room
 
 
Challenges
Technical challenges (among other contractors)
Shock, vibration and EMC requirements
Vulnerability requirements for certain systems
Space constraints for the routing & handling and transporting of ACCU & AHU ,pipe-work and insulation.
Sound level restrictions
Incompatibility of new equipment and control system with some existing equipment
Complete the machine instrumental shortage
Loop-check
Time schedule limit
HSE regulations
 
 
Scope of work
 
ARMANIK’s scope of work for the above project comprised:
 
Pre-contract
Co-writing technical specifications ,site visit and general arrengement.
 
Post-contract
Complete followed by delivery, installation, commissioning, FAT, HAT, SAT,training activities.
 
System and process was constructed by PFC co in the sought of Iran .
 

Scope of service

Among several smaller items of equipment, the following main services was supplied.
                                            
Site Visit, Check Foundations, AHU & ACU Visual Check, Find Out Piping & Cabling Route.
Design Interconnection Copper Pipe  Size& Route For Liquid &Suction Line
Material Take Off Configuration Including Copper Pipe , Elbow ,Connectors, Support, Insulation,…
Hanging & Installation AHU units on Base Frame With Vibration Absorbers Pad 
Reassembling Ahu's Section By Stiffeners
Hanging & Installation ACU units on Base Frame With Vibration Absorbers Pad 
Pipe Cutting , Fitting , Install Pipe Support ,Silver Brazing ,painting ,…. For Each Circuit .
Washing Circuits By Refrigerant R141-B
Nitrogen Pressure (Leak) Test for 24 to 48 hours According to the Site Specification And Remove Leakages
Install Insulation And Cladding.
Connect All Wires To Local & Control Panel And Instruments
Install All Instruments Such TT,HT,Pressure Transmitter ,Motorized Damper,...
Logic Test , Check Machine Inside Controllers & Switches.
Vacuuming ,Set The Core Driers , Change The Compressor Oil
Cleaning &Washing Machine Coils , All inside Equipment and Install AHU's Filters.
Charging refrigerant , Start-Up Circuits Separated And Partially.
Operation & Maintenance For 48 Hours Non Stop Working.
SAT activities 
Check the acceptance criteria
Clients expert training 
Performance Test

FROOZAN Off-Shore Wellhead Platform F-18